Client

Confidential

Scope

Deconstruction of a 9-storey ‘live’ link building and façade infills to establish two separate office buildings.

Project Partners

  • Credit Suisse
  • Arcadis
  • TP Bennett
  • ARUP
  • 4B Projects
  • LS Estates
  • Todd Architects
  • FT Squared 

Duration

59 Weeks

Size

20,000 sq ft

Location

Canary Wharf

Project Description

Our Link Bridge project consisted of the removal of a link bridge between two existing office buildings, 17 and 20 Columbus Courtyard, and façade upgrade to establish two separate office buildings with improved thermal performance.  

Situated in the heart of Canary Wharf, the logistics for this project was extremely challenging and required a robust traffic management plan. Specific restrictions for working in Canary Wharf also had to be worked through, which we successfully managed by developing an excellent working relationship with Canary Wharf Group.

The building was also live throughout the deconstruction and façade works requiring a collaborative working with key stakeholders involved.

Key Features

  • Complex logistics
  • Collaborative working with multiple stakeholders
  • Live building throughout the works